How to take off a slab and footings from plans
A step-by-step guide to measuring a residential slab and footings from the drawings — slab area, edge beams, waffle pods, reinforcement, and the deductions that are easy to miss.
Insights Published · 9 min · By Scaleline
For Australian builders of new homes.
To take off a slab and footings from plans, read the structural drawing rather than the architectural, measure the slab area in square metres and the edge beams and strip footings in linear metres, then account for waffle pods, reinforcement and the deductions you might otherwise skip. It’s one of the most common first trades builders measure, and one of the easiest to get subtly wrong. Here’s the order we work in, line by line.
Start from the structural plan, not the architectural
A slab take-off from plans begins by picking the right sheet. The architectural plan tells you room sizes; the structural plan tells you what’s actually being poured. Slab thickness, edge beam sizes, pod layout and reinforcement all live on the structural drawing, and that’s the sheet that governs the concrete and steel quantities.
Read the slab outline off the structural plan’s slab layout, then confirm it against the floor plan for the overall footprint. The two should agree on the outside of the building; if they don’t, something’s been drawn twice or a set-back wall hasn’t been picked up. Settle that disagreement before you measure anything, because every quantity below it inherits the mistake.
The slab itself is area: length by width, in square metres, to the outside of the slab edge — not to the outside of the brickwork. Allow for any step-downs, verandahs or alfresco areas that are poured as part of the same slab but drawn as a separate zone. Each zone is a separate area line so the concretor can price it separately.
Where the drawing gives a slab thickness that varies — a thicker edge, a thinner alfresco — carry the thickness on each area line rather than averaging it. Concrete is priced by volume, so area alone is only half the quantity until the thickness is attached.
Edge beams and strip footings in linear metres
The footing take-off is linear, not area. Around the perimeter of a conventional slab you have an edge beam; on a strip-footing job you have trenches running under load-bearing walls. Both are measured in linear metres, taken off the plan’s beam and footing layout with the beam size read off the section or the schedule.
Count the full perimeter of the slab for the edge beam, then add the internal beams. Internal thickening beams — the ones that run under walls or support a change in level — are linear metres too, and they’re the lines most likely to be left off a hand take-off because they don’t sit on the outside edge. If the drawing calls them out as a “thickened slab edge” or a specific beam type, that’s a separate line, not part of the slab area.
For each beam you also need its size, because concrete is priced by depth and width. A 300mm deep edge beam is a different rate to a 450mm one. Take the size off the beam schedule or the typical detail, and keep it on the same line so the quantity and its section travel together.
Waffle pod slabs: what changes in the quantities
A waffle pod slab quantities take-off looks different from a conventional slab because the concrete isn’t poured as a solid slab. The pods displace a large part of the volume, and the concrete actually placed is concentrated in the ribs between pods and the beams around them.
For a waffle slab, measure the slab area as before, then measure the ribs as linear metres — the number of ribs in each direction times their length. The pod count comes off the pod layout: count the pods per grid, and make sure the count covers the full footprint including any half-pods at the edges. The reinforcement in a waffle slab also differs, because the ribs take the steel rather than the slab face.
The common error on waffle slabs is treating them like a conventional slab and pricing the full area at a solid-slab rate. The material is less, but the formwork and the pod supply are more. Keep the ribs, the pods and the beams as their own lines so the concretor can price what’s actually on site.
Reinforcement: measure area, not weight
Steel is taken off by area and length, not by guessed weight. For a conventional slab you’ll have a mesh area — the slab area plus laps and a wastage allowance — read off the mesh schedule. For beams and footings you have bar counts and lengths: the number of bars per beam, times the beam length, times the number of beams, plus laps, chairs and ties read off the typical details.
Don’t convert to tonnes yourself. The reinforcement supplier and the concretor price by the bar schedule and the mesh area; if you hand them a tonne figure you’ve already made an assumption about bar size and spacing that belongs to them. Give them the raw quantities — area, counts, lengths — and let the rate carry the conversion.
Read the laps off the structural notes, not off a rule of thumb. A lap length is driven by the bar diameter and the concrete specification, and it changes the bar count on the long runs. Chairs and spacer counts come off the typical details and are usually expressed per square metre of slab, so they scale with the area line rather than being counted one by one.
The deductions and allowances that change the total
The quantity blows out on a slab when a small deduction is skipped. The most common ones are the recesses and step-downs — a dropped slab for a shower, a rebate for a garage door, a set-down for a tiled area. Each of those is less concrete, and each should reduce the area or add a line for the reduced thickness.
On the allowance side, keep concrete wastage and mesh laps as explicit factors you can show, not a round number buried in the rate. A 5% waste allowance on concrete and the mesh lap schedule are legitimate lines; they just need to be visible so the builder can see what’s been assumed.
The other line that goes missing is the footing to the external piers or columns, if the job has them. A verandah post or a steel column often sits on its own pad footing drawn on a separate detail, and it’s measured as a count of pads with their size, not folded into the strip footing length. The same goes for the pier holes under a bearer-and-joist floor — they’re a count per pier with a depth, and they belong to the substructure, not the slab.
How we measure a slab
Our engine reads the structural slab layout’s vector and text layers first — the dimensions and callouts the drafter put there — and uses vision only to resolve what the annotations don’t pin down, such as a pod layout that’s drawn but not called out. Every slab line in the report carries its source: the sheet and the dimension it came from, plus a confidence mark. Anything below the bar gets a human check before the report ships.