SA wind region and soil class: why site classification shapes the take-off
How SA wind regions and AS 2870 soil classes change the quantities a builder has to price — and why an Adelaide take-off has to read the local conditions, not a national average.
Insights Published · 8 min · By Scaleline
For Australian builders of new homes.
An Adelaide take-off that ignores the SA wind region and the soil class is measuring a house that isn’t there. The wind classification on the drawings and the site classification from the geotech report change the footings, the bracing, the tie-down and the slab long before a single rate is applied. Two builders on opposite sides of the same suburb can be pricing different quantities for what looks like the same floor plan, because the ground and the wind under them are different. Here’s how the two classifications work and where they show up in the quantities.
Wind region: what the classification changes
The SA wind region is assigned under the wind standard that classifies residential sites by how hard the wind can load a building, and the class is written on the drawings as a design parameter, not an opinion. In South Australia the classification comes in a small number of bands — most Adelaide sites sit in the moderate ones, but the coastal fringe, the hills and exposed open sites step up a band or more.
The class drives three families of quantities. First, wall bracing — the length of bracing panels and the tie-down that anchors them — rises with the wind class, and a higher class adds panels and holds-down to walls that a lower class would leave unbraced. Second, roof tie-down — the strapping, bolts and brackets that keep the roof on the frame scale with wind load, and the difference between two adjacent bands is a real change in the steel and fixings count. Third, openings and glass — windows and sliding doors are sized and selected for the wind pressure at their location, and an exposed site can push a window spec up a band, which changes the allowance on the joinery line.
The trap is treating the wind class as a footnote. It isn’t. A plan that says “N3” and a plan that says “N2” are not the same building from a quantities point of view, even when the room layout is identical, because the bracing and tie-down schedules sit on the wind class the drafter assumed. If you price the floor plan and skip the classification, you’re pricing someone else’s assumption.
Soil class: what AS 2870 site classification changes
The soil class comes from a different standard again — the one that classifies a site by how much the ground moves with moisture, from the least reactive sands through the moderately reactive clays to the highly and extremely reactive clays and the problem sites that need engineering. The class is determined by a geotechnical report, and it is the single biggest driver of the substructure quantities.
On a low-reactivity site the footing might be a straightforward strip or a conventional slab. On a highly reactive clay the same floor plan wants a deeper, more engineered footing — a stiffened raft slab with more reinforcement, deeper edge beams, or piered footings down to a stable depth. That isn’t a small tweak; it’s a materially different concrete volume, steel weight and excavation allowance, and it all lives in the site class rather than on the architectural drawing.
The class also decides the slab design assumptions the builder carries. The reinforcing mesh, the beam depth and spacing, and the articulation details all respond to ground movement, and they scale with the class. A builder who copies the quantities from a flat sandy site in the west to a reactive clay site in the north-east is carrying the wrong slab before the job starts.
Where the two classifications meet in the take-off
Wind and soil aren’t two separate footnotes — they meet in the structural trades, and that’s where an Adelaide site classification take-off earns its keep. The slab and footings carry the soil class; the wall frame and roof carry the wind region; and the tie-down that connects the two carries both, because the building has to be anchored to the ground that moves and to the roof that’s being loaded.
The line items that change are the ones a hand take-off is most likely to gloss over. The bracing panels and their lengths, the strapping and the hold-down brackets, the footing depth and beam size, the mesh area and the pier count. Each of them is a quantity read off a schedule that only exists because someone applied the wind class and the soil class to the plan. Skip the classifications and those schedules never make it into the numbers.
This is also why a take-off that names its sources matters. A quantity should carry the classification it came from — “slab as per H1 site class”, “bracing as per N3 wind” — so the builder can see why a line is what it is and challenge it if the assumptions don’t match the site. That’s the same source-marking discipline we apply across every trade, and you can see how it reads on our method page.
Why local matters more in Adelaide than a national average implies
South Australia earns its reputation for reactive soils. Large parts of the Adelaide basin sit on clays that move significantly between a wet winter and a dry summer, and the plains, the foothills and the coastal strip each behave differently. The site class that governs a build in one suburb can be two bands away from the site class ten minutes down the road, and there is no national average that reconciles them.
The same is true of the wind. Adelaide’s wind isn’t cyclonic, so the classification bands are the moderate non-cyclonic ones, but the exposure varies sharply — an open site on the plains, a ridgeline block in the Hills and a sheltered street all load the building differently even within the same nominal band. The classification captures that exposure, and a builder pricing from a template is quietly assuming the exposure is average when it very often isn’t.
Local matters for a second reason: the authority that matters is the site. A geotech report and a wind classification are written for a specific address, not for a postcode, and the honest quantities come from reading that report and those drawing notes against the plan. An offshore or template price has no way to see them, which is one of the concrete differences we walk through in our piece on onshore vs offshore estimating.
How the classifications reach the quantities
In practice the chain runs: site report and structural notes first, then the schedules they drive, then the quantities read off those schedules. The soil class sets the footing and slab parameters; those parameters become the beam sizes, the mesh and the pier schedule on the structural drawing. The wind class sets the bracing and tie-down parameters; those become the panel lengths and the hold-down schedule. The take-off is the last step, but it’s the step that has to trace every line back to the classification that produced it.
We read that chain the same way we read any trade — the vector and text layers first, the schedules and notes the drafter put there, and a local estimator to resolve what the annotations leave out. Where the classification is written on the sheet, the quantity inherits it and the report says so. Where a slab or footing depends on it, the line carries the site class so the concretor can price what’s actually being poured, in the same spirit as our slab and footings take-off guide.
The point of reading the classifications isn’t to be clever about geology. It’s that two identical floor plans on different ground are two different jobs, and the only way to price them honestly is to start from the site conditions the drawings and the reports actually state. We measure new homes across Australia the same way: the class on that site’s drawings, not a state average. Adelaide is the worked example above.
Check the classifications on your next job
Before you price the next plan, check the two notes that are easy to skip: the wind class on the structural drawing and the site class on the geotech report. If either is missing, the quantities below them are an assumption waiting to be found, and the time to find it is before you’ve poured anything.
You can see how the source marks read on a real job in our sample report, and if you want to check our numbers against a build you already know, book a blind test →.
This is Scaleline’s view. We measure residential jobs from drawings — we don’t price them, and we don’t sell software. Where we mention how we work, it’s to be useful, not to oversell.