Tender package checklist for a new home
What to check before you send drawings and a bill of quantities to subcontractors for pricing — drawing revisions, scope split by trade, sourced quantities, written exclusions, and a closing date for questions.
Insights Published · 7 min · By Scaleline
For Australian builders of new homes.
A tender package checklist for a new home comes down to five checks before anything goes out to a subcontractor: is every drawing the same revision, does each trade get only what it needs, is the bill of quantities sourced rather than just a list of numbers, are the exclusions written down, and is there a closing date with a clear way to ask questions. Skip any one of these and the quotes that come back won’t be comparable — you’ll be pricing four different jobs instead of one.
Check every drawing in the pack is the same revision
Mixed revisions in a pricing pack are one of the most common reasons quotes come back inconsistent. One construction tendering guide puts it plainly: if the structural drawings a subcontractor is quoting from are a revision behind the architectural set, you end up comparing bids built on different buildings.
Before you send anything, open every sheet and check the revision letter or number in the title block against the most recent issue you have. If your architect or drafter maintains an issue register or a revision history, cross-check against that rather than against your own memory of which version is current. A set that’s partly current and partly superseded is worse than a set that’s incomplete but consistent — at least an incomplete set gets flagged as missing, where a mixed-revision set looks complete and quotes against the wrong building.
Spell out which drawings and which trades go to which subcontractor
Not every subbie needs the full set. A concreter needs the structural and architectural drawings for footings and slab; an electrician needs the lighting and power layout; a cladding installer needs the elevations and a specification if one exists. A tender set for a whole-of-build quote typically bundles the drawing and condition-of-approval documents, the construction-approved general arrangement drawings, lighting and electrical layouts, finishes schedules and the specification — the same logic applies at trade level, just scoped down to what that one trade is pricing.
Sending a trade everything you have isn’t generous, it’s confusing — the subbie has to work out which sheets are relevant to them, and a mistake in that filtering can mean a quote built off the wrong drawing. If your bill of quantities is already broken into trade-by-trade blocks, send each subcontractor their own block rather than the full document; it’s the same reason a BOQ is structured that way in the first place — you can hand one trade’s section to the subbie who prices it without exposing the rest of the job.
Make sure the quantities are sourced, not just numbers
A bare quantity — “external walls, 206 m²” — asks a subcontractor to trust your counting. A sourced quantity, with the source page and the dimension it was measured off, lets them check it before they price it. If you’re assembling your own bill of quantities for the pack, note on each line where the number came from; if you’re working from a measured take-off, that evidence chain is already built in, and you can see what it looks like on the sample report.
This matters most when you’re sending the same scope to more than one subcontractor. Three quotes rarely line up because each trade measured the job differently — give every trade the identical, sourced quantity and the only thing left to vary is their rate, which is the comparison you actually want.
Write the exclusions down, not just the inclusions
A pricing pack that only lists what’s included leaves every gap open to interpretation — and gaps left open get priced differently by every subcontractor who reads them differently. Tendering guidance on this point is consistent: checking for inclusions and exclusions is listed as a standard step in comparing tenders, because an unstated exclusion shows up later as a variation, not as a line item you can compare up front. Common gaps worth stating explicitly either way include crane or plant hire, temporary power and site facilities, and any fixtures or fittings supplied separately — whatever applies to your job, put the exclusion in writing rather than assuming it’s obvious.
Set a closing date and a fair way to answer questions
Give every subcontractor the same deadline for their quote, and the same cut-off for asking questions before that deadline. When a subcontractor asks a clarifying question, the fair move — and the one that keeps the comparison honest — is to send that answer to every other subcontractor who received the pack, not just the one who asked. That’s standard practice in tendering: queries are a normal part of the process, and keeping the answers shared is what stops one subcontractor quoting on more information than the others.
Before you build the pack
Most of this checklist assumes you already have a bill of quantities and a current drawing set to build the pack from. If you don’t yet have quantities you can hand to more than one subcontractor with confidence, that’s the step before this one — see how the measuring works or start with one floor plan or a single trade and build the rest of the pack once the quantities are in hand.
This is Scaleline’s view. We measure residential jobs from drawings — we don’t price them, and we don’t sell software. Where we mention how we work, it’s to be useful, not to oversell.